Building envelope work sequence
Envelope work closes the building against rain, wind and heat. The high-risk points are openings, flashings, sealant joints and moisture bridges where several trades meet.
Volver a todas las secuencias
P谩ginas conectadas
Esta secuencia conecta calculadora, checklist y coste de errores para mantener planificaci贸n y riesgo en un sistema.
Secuencia recomendada de trabajo
01 Prepare openings and support conditions
Make the opening fit the product before the product arrives.
- Check opening size, squareness, level, support and fixing zones.
- Repair weak edges and confirm sill slope or water path.
- Verify that waterproofing, facade and interior finish thicknesses align.
Punto de control: Window and door installation should not start until openings are measured and corrected.
Herramientas, equipos y acceso: Laser measure, Level, Masonry repair tools, Opening checklist
02 Install frames, flashings and weather seals
Close the water path at each opening and edge.
- Fix frames with correct packers, anchors and movement allowance.
- Install sill flashings, drip edges, tapes and perimeter sealant.
- Protect exposed joints until facade and interior returns are complete.
Punto de control: Do not cover perimeter joints until fixings, packers, flashing and sealant backing are inspected.
Herramientas, equipos y acceso: Frame setting tools, Sealant gun, Flashing snips, Foam gun, Torque driver
03 Test water path and close interfaces
Confirm the envelope works as a system before finishing returns.
- Check drainage path at sills, thresholds and facade interfaces.
- Inspect moisture bridge risks around plinths and exposed edges.
- Record completed details before interior and exterior finishes hide them.
Punto de control: Interior finishing should wait until envelope interfaces are weather-tight and recorded.
Herramientas, equipos y acceso: Water spray kit, Moisture meter, Inspection mirror, Photo log
Herramientas, equipos y acceso
Measurement and setting
- Laser measure
- Level
- Packers
- Frame clamps
Weather sealing
- Sealant gun
- Flashing snips
- Foam gun
- Tape roller
Inspection
- Water spray kit
- Moisture meter
- Inspection mirror
- Photo log
Consumos de material para planificaci贸n
Los consumos son referencias de planificaci贸n. Las cantidades finales deben comprobarse con planos, especificaciones, normativa local y fichas de proveedor.
| Material o recurso | Base | Rango de planificaci贸n | Unidad | Nota |
| Perimeter sealant | Joint length | 6-12 | lm/cartridge | Joint geometry controls final rate. |
| Flashing tape | Opening perimeter | 1.05-1.20 | lm/lm | Allows laps, corners and waste. |
| Frame packers and fixings | Opening unit | 6-14 | pcs/unit | Adjust to size and wind load. |
| Opening repair mortar | Opening perimeter | 0.05-0.15 | m2/lm | Planning allowance for edge correction. |
Controles de calidad antes de avanzar
- Openings are measured, corrected and signed off before product install.
- Sill slope, flashing and drip path are visible.
- Perimeter sealant has correct backing and joint geometry.
- Moisture bridge risks are checked before interior returns close.
T茅rminos relacionados
Capa exterior que separa interior y clima.
Detalle de evacuaci贸n de agua alrededor de ventanas y puertas exteriores para evitar que la lluvia entre en el muro.
Junta flexible con sellador para proteger interfaces con movimiento.
Ruta no deseada que permite a la humedad saltarse una capa de protecci贸n y entrar en la construcci贸n o el acabado.
Nivel de prestaciones del sistema de vidrio.