Waterproofing work sequence

Waterproofing succeeds or fails at interfaces: substrate, corners, drains, penetrations and movement joints. The sequence must keep details visible until they are inspected and tested.

Volver a todas las secuencias

P谩ginas conectadas

Esta secuencia conecta calculadora, checklist y coste de errores para mantener planificaci贸n y riesgo en un sistema.

Secuencia recomendada de trabajo

01

Prepare substrate and details

Make the base clean, stable and shaped for water movement.

  • Check slope to drains, surface strength, moisture and crack condition.
  • Form coves, corners, upstands and pipe penetration details.
  • Prime only after dust, laitance and loose material are removed.

Punto de control: Membrane application should not start until slope, substrate and penetration details are accepted.

Herramientas, equipos y acceso: Moisture meter, Scraper, Vacuum, Primer roller, Slope gauge

02

Install membrane and reinforcement

Create a continuous system through field areas and critical details.

  • Apply the specified coats, sheets or membrane system at required thickness.
  • Reinforce corners, drains, joints, pipe sleeves and thresholds.
  • Protect fresh membrane from dust, trades and mechanical damage.

Punto de control: Do not tile, screed or cover until membrane thickness and critical details are checked.

Herramientas, equipos y acceso: Wet film gauge, Detail brush, Roller, Membrane scissors, Joint tape

03

Test, protect and release to finishes

Prove the waterproofing before it becomes inaccessible.

  • Carry out flood, ponding or local water testing where suitable.
  • Photograph drains, corners, upstands and penetrations.
  • Install protection before screed, tile or equipment installation.

Punto de control: Finish works should not proceed until test result, protection and photo evidence are complete.

Herramientas, equipos y acceso: Water test kit, Stopper, Moisture meter, Protection board tools

Herramientas, equipos y acceso

Substrate preparation

  • Vacuum
  • Scraper
  • Moisture meter
  • Slope gauge

Application

  • Primer roller
  • Detail brushes
  • Wet film gauge
  • Joint tape tools

Testing and protection

  • Water stoppers
  • Moisture meter
  • Protection board cutter
  • Photo log

Consumos de material para planificaci贸n

Los consumos son referencias de planificaci贸n. Las cantidades finales deben comprobarse con planos, especificaciones, normativa local y fichas de proveedor.

Material o recurso Base Rango de planificaci贸n Unidad Nota
Liquid waterproofing membrane Waterproofed area 1.5-2.5 kg/m2 Use supplier dry-film thickness for final quantity.
Primer Prepared substrate 0.15-0.30 kg/m2 Depends on porosity.
Corner tape Internal corners and movement joints 1.00-1.20 lm/lm Allows laps and waste.
Protection layer Membrane area 1.05-1.15 m2/m2 Required before high-risk follow-on trades.

Controles de calidad antes de avanzar

T茅rminos relacionados

Junta sellada

Junta flexible con sellador para proteger interfaces con movimiento.

Preparaci贸n del soporte

Limpieza, nivelaci贸n, imprimaci贸n, control de humedad y verificaci贸n de compatibilidad antes de instalar acabados.