Pre-construction work sequence
Pre-construction turns an uncertain site into a controlled work front. The goal is to verify baseline data, protect access and remove avoidable constraints before long-lead purchasing and main works begin.
Kembali ke semua urutan
Halaman produk terkait
Urutan ini terhubung dengan kalkulator, checklist dan halaman biaya kesalahan agar planning dan kontrol risiko tetap satu sistem.
Urutan pekerjaan yang direkomendasikan
01 Confirm baseline site data
Lock the information that the calculator and design team depend on.
- Check boundary, levels, access constraints and known utility routes.
- Create photo records of existing structures, vegetation, drainage and neighboring risks.
- Mark survey benchmarks and protect them from site traffic.
Hold point: Do not start excavation pricing or procurement until survey control, access limits and known constraints are recorded.
Alat, peralatan dan akses: Total station or level, Drone or photo set, Marking paint, Site constraint register
02 Set logistics, access and temporary protection
Make sure labor, plant, deliveries and waste can move without damaging the site.
- Define entry route, laydown area, turning radius and delivery windows.
- Install temporary fencing, signage and protection to retained finishes or landscape.
- Separate clean access, material storage and waste routes where the site allows.
Hold point: Main works should not start until access, laydown and waste handling are visible on site.
Alat, peralatan dan akses: Temporary fence panels, Compactor, Road plates or crushed base, Safety signage
03 Control temporary water and utilities
Prevent water and temporary services from creating delay or hidden site damage.
- Plan temporary drainage away from excavation, storage and neighboring properties.
- Provide temporary power and water with safe routing and clear shutoff points.
- Check that temporary works do not conflict with future foundation or service routes.
Hold point: Temporary drainage and utilities must be inspected before excavation, foundation works or rainy-season mobilization.
Alat, peralatan dan akses: Submersible pump, Silt fence, Temporary distribution board, Hoses and cable ramps
Alat, peralatan dan akses
Survey and records
- Total station or laser level
- Measuring wheel
- Photo log
- Benchmark tags
Temporary works
- Fence panels
- Compactor
- Pump
- Cable ramps
- Temporary lighting
Control documents
- Site constraint register
- Access plan
- Temporary utilities plan
Norma konsumsi material untuk perencanaan
Rentang konsumsi adalah benchmark perencanaan. Kuantitas final harus dicek terhadap gambar, spesifikasi, kode lokal dan data supplier.
| Material atau resource | Basis | Rentang rencana | Unit | Catatan |
| Temporary access base | Heavy access area | 0.10-0.25 | m3/m2 | Use higher depth for soft ground or repeated truck traffic. |
| Temporary drainage route | Open work area | 0.10-0.25 | lm/m2 | A planning allowance before detailed stormwater design. |
| Survey and condition photos | Project | 40-120 | photos | Useful as evidence if access, neighbor or drainage claims appear later. |
Quality gate sebelum lanjut
- Survey benchmark and boundary records are documented.
- Access, laydown, waste and temporary utility routes are agreed.
- Rainwater and sediment control are in place before earthworks.
- Temporary works do not block future foundation or engineering routes.
Istilah glossary terkait
Tingkat kesulitan logistik ke area proyek.
Pemindahan sumbu dan geometri bangunan ke lapangan.
Titik referensi survei untuk kontrol elevasi dan posisi.
Temporary structures, services or controls used to build the permanent works safely and efficiently.
Manajemen aliran air di area sekitar bangunan.