Urutan kerja
Roof work sequence
Roof work is a water-control system, not only a finish. The correct sequence protects slope, membrane continuity, flashings, drains and overflow before leaks become interior damage.
Kembali ke semua urutan
Halaman produk terkait
Urutan ini terhubung dengan kalkulator, checklist dan halaman biaya kesalahan agar planning dan kontrol risiko tetap satu sistem.
Urutan pekerjaan yang direkomendasikan
01 Prepare roof base and falls
Give water a reliable path before waterproofing starts.
- Clean the roof base and remove laitance, dust and loose material.
- Set out falls to primary drains, scuppers and overflow points.
- Confirm upstands, parapet heights and equipment plinths.
Hold point: Waterproofing should not begin until falls, low points and drain locations are visible and checked.
Alat, peralatan dan akses: Laser level, Straightedge, Screed tools, Drain templates
02 Install membrane, flashings and terminations
Create continuous waterproofing around edges, penetrations and vertical faces.
- Prime the base and install membrane or liquid system to supplier requirements.
- Reinforce corners, outlets, penetrations, parapets and movement joints.
- Protect membrane before other trades return to the roof.
Hold point: No covering layer or equipment installation should proceed until membrane continuity and flashings are inspected.
Alat, peralatan dan akses: Primer roller, Membrane tools, Detail brushes, Heat gun or torch
03 Test drainage, overflow and protection
Prove the roof can remove water before interior finishes are exposed.
- Check drain strainers, overflow routes and downpipe continuity.
- Run ponding or controlled water test where appropriate.
- Install protection layer and record hidden details.
Hold point: Interior ceiling closure should wait until roof drainage and waterproofing evidence are complete.
Alat, peralatan dan akses: Water hose, Drain camera if needed, Moisture meter, Photo log
Alat, peralatan dan akses
Level and slope control
- Laser level
- Straightedge
- Drain templates
- Screed tools
Waterproofing
- Primer rollers
- Detail brushes
- Membrane tools
- Protection board knife
Testing
- Water hose
- Stopper
- Moisture meter
- Inspection camera
Norma konsumsi material untuk perencanaan
Rentang konsumsi adalah benchmark perencanaan. Kuantitas final harus dicek terhadap gambar, spesifikasi, kode lokal dan data supplier.
| Material atau resource | Basis | Rentang rencana | Unit | Catatan |
| Falls buildup | Roof area | 0.03-0.08 | m3/m2 | Planning range before detailed slope drawing. |
| Roof membrane waste and laps | Waterproofed area | 10-20 | % | Higher for corners and penetrations. |
| Primer | Roof substrate | 0.15-0.30 | kg/m2 | Supplier data sheet governs final quantity. |
| Protection layer | Roof membrane area | 1.05-1.15 | m2/m2 | Allows cuts and edge detailing. |
Quality gate sebelum lanjut
- Roof falls lead to drains without reverse slope.
- Membrane details at drains, parapets and penetrations are inspected.
- Overflow path is confirmed separately from primary drainage.
- Protection and hidden detail photos are complete before covering.
Istilah glossary terkait
Gradien atap untuk pembuangan air hujan.
Jalur cadangan pembuangan air saat hujan ekstrem.
Sistem pelindung agar air tidak menembus elemen bangunan.
Detail sambungan yang memungkinkan pergerakan terkontrol antar elemen.
Tingkat pengaruh lingkungan seperti hujan dan garam.