BuildBudgeter

Bali

Bali construction cost per m2

Cost per square meter is the fastest way to compare options, but it also hides the most important differences. This page translates the BuildBudgeter stage model into simple m2 planning bands and explains when that shortcut is safe enough.

Back to cost guides

Budget snapshot

Location Bali
Planning range IDR 7.8M-18.5M / m²
Best for Comparing rough budgets before choosing finish level, engineering scope, and pool specification.

Example planning scenarios

Scenario Area / basis Specification Planning range Unit range Important note
Basic shell plus standard fit-out 120-180 m² Simple structural grid, restrained glazing, standard plumbing and electrical systems. IDR 0.95B-2.80B IDR 7.8M-15.5M / m² Low range assumes no major retaining, no premium imported finishes, and clear drawings.
Standard villa build 250-350 m² Normal structure, roof, envelope, waterproofing, split AC, and mid-range finishes. IDR 2.25B-5.95B IDR 9.0M-17.0M / m² Good reference for early investor conversations.
Higher-spec build 400-600 m² Larger spans, premium finishes, higher MEP load, larger wet areas, or difficult access. IDR 4.80B-11.10B IDR 12.0M-18.5M / m² Use stage-level review before treating this as a fixed target.

How to use this guide

Use this page for feasibility, not procurement. A contractor tender still needs drawings, quantities, and a defined material schedule.

If two options differ by less than 10-15%, compare them by stage instead of trusting the average m2 rate.

Scope assumptions

Usually included

  • Normal residential shell, envelope, engineering, waterproofing, and finishing assumptions.
  • Stage-level cost logic used by the calculator.

Usually excluded or priced separately

  • Furniture, loose equipment, professional fees, land, taxes, and financing.
  • Extreme slope stabilization, unusual foundations, or non-standard authority requirements.

What changes the number

Connect this guide to the product workflow

The cost guide is useful only when it is tied back to stage pages, checklists, mistakes, and the work sequence for execution control.

Related glossary articles

Material consumption rate

A planning quantity of material expected per unit of work, such as kg per m², m³ per m² or linear meters per room.

Productivity rate

The amount of work a crew or resource can complete in a defined time, usually measured per day, shift or labor-hour.

FAQ

Why does cost per m2 vary so much?

Because the rate mixes structure, envelope, MEP, finishes, site works, access, and risk. Two buildings with the same area can have very different wet-area count, roof shape, and engineering scope.

When should I stop using the m2 shortcut?

Stop using it when you are choosing a contractor, signing a contract, changing MEP scope, or approving high-value finishes. At that point the estimate should move to stage and work-package detail.