Usually included
- Normal residential shell, envelope, engineering, waterproofing, and finishing assumptions.
- Stage-level cost logic used by the calculator.
Bali
Cost per square meter is the fastest way to compare options, but it also hides the most important differences. This page translates the BuildBudgeter stage model into simple m2 planning bands and explains when that shortcut is safe enough.
| Scenario | Area / basis | Specification | Planning range | Unit range | Important note |
|---|---|---|---|---|---|
| Basic shell plus standard fit-out | 120-180 m² | Simple structural grid, restrained glazing, standard plumbing and electrical systems. | IDR 0.95B-2.80B | IDR 7.8M-15.5M / m² | Low range assumes no major retaining, no premium imported finishes, and clear drawings. |
| Standard villa build | 250-350 m² | Normal structure, roof, envelope, waterproofing, split AC, and mid-range finishes. | IDR 2.25B-5.95B | IDR 9.0M-17.0M / m² | Good reference for early investor conversations. |
| Higher-spec build | 400-600 m² | Larger spans, premium finishes, higher MEP load, larger wet areas, or difficult access. | IDR 4.80B-11.10B | IDR 12.0M-18.5M / m² | Use stage-level review before treating this as a fixed target. |
Use this page for feasibility, not procurement. A contractor tender still needs drawings, quantities, and a defined material schedule.
If two options differ by less than 10-15%, compare them by stage instead of trusting the average m2 rate.
The cost guide is useful only when it is tied back to stage pages, checklists, mistakes, and the work sequence for execution control.
A planning quantity of material expected per unit of work, such as kg per m², m³ per m² or linear meters per room.
The amount of work a crew or resource can complete in a defined time, usually measured per day, shift or labor-hour.
Barrier systems preventing water penetration.
Ground-level water management around the building.
Because the rate mixes structure, envelope, MEP, finishes, site works, access, and risk. Two buildings with the same area can have very different wet-area count, roof shape, and engineering scope.
Stop using it when you are choosing a contractor, signing a contract, changing MEP scope, or approving high-value finishes. At that point the estimate should move to stage and work-package detail.