BuildBudgeter

Work sequence

Structural frame work sequence

The structure stage must keep load path, geometry, embeds and concrete quality under control. Errors are expensive because they are usually found after walls, services or finishes depend on the frame.

Back to all sequences

Connected product pages

This sequence is connected to the stage calculator, checklist and mistake-cost pages so planning, execution and cost risk stay in one system.

Recommended sequence of work

01

Plan load path, formwork and embeds

Coordinate the frame before concrete hides decisions.

  • Check columns, beams, slabs, openings, construction joints and temporary supports.
  • Confirm embedded plates, sleeves, anchors, balcony edges and stair interfaces.
  • Review pour sequence, access, pump route and curing method.

Hold point: Do not close formwork until embeds, openings, reinforcement access and pour method are coordinated.

Tools, equipment and access: Formwork system, Shop drawings, Sleeve templates, Temporary props

02

Fix reinforcement and pour concrete

Deliver structural capacity with inspectable cover, spacing and consolidation.

  • Install rebar with correct laps, chairs, spacers and congestion management.
  • Inspect cover before pour and keep access for vibration.
  • Place concrete in controlled lifts or bays and protect against rapid drying.

Hold point: Concrete should not be poured until rebar, cover, openings and embeds are signed off.

Tools, equipment and access: Rebar tools, Cover meter or gauge, Concrete vibrator, Pump line, Curing covers

03

Verify geometry, curing and as-built records

Prevent frame deviations from becoming finish and MEP problems.

  • Check column alignment, slab levels, stair geometry and opening dimensions.
  • Maintain curing period and protect exposed concrete edges.
  • Record as-built deviations before envelope and engineering rough-in.

Hold point: MEP rough-in and envelope work should not start until critical dimensions and openings are verified.

Tools, equipment and access: Laser level, Plumb laser, Moisture/curing log, As-built photo set

Tools, equipment and access

Frame control

  • Laser level
  • Plumb laser
  • Tape
  • Gridline tags

Concrete operations

  • Vibrator
  • Pump hose
  • Concrete bucket
  • Curing sheet

Rebar and embeds

  • Rebar cutter
  • Tie wire tool
  • Cover spacers
  • Embed templates

Planning material consumption norms

Consumption ranges are planning benchmarks. Final quantities must be checked against drawings, specifications, local codes and supplier data sheets.

Material or resource Basis Planning range Unit Planning note
Reinforcement steel Structural concrete 90-160 kg/m3 Concept allowance; final design governs.
Formwork contact area Concrete volume 5-10 m2/m3 Depends on wall, column, beam and slab mix.
Curing compound or cover Exposed concrete area 1.00-1.10 m2/m2 Protects early strength and surface quality.
Embed and sleeve allowance MEP crossing or facade support 1 set/item Every embed should have an owner and drawing reference.

Quality gates before moving forward

Related glossary terms

Load path

Continuous route by which gravity, wind, and other forces move through the structure into the foundation.

Formwork

Temporary mould and support system that holds wet concrete in the required shape until it can carry itself.

Concrete cover

Distance between reinforcement and concrete surface that protects steel and helps structural performance.

Construction joint

Joint formed where concrete placement stops and later continues, requiring structural and waterproofing continuity.

Concrete curing

Post-pour moisture and temperature control that helps concrete develop strength and durability.