Foundation work sequence

Foundation work should move from verified levels to excavation, base preparation, reinforcement, concrete, waterproofing, drainage and controlled backfill. Skipping checks here makes every later stage more expensive.

Volver a todas las secuencias

P谩ginas conectadas

Esta secuencia conecta calculadora, checklist y coste de errores para mantener planificaci贸n y riesgo en un sistema.

Secuencia recomendada de trabajo

01

Set out excavation and control levels

Translate drawings into real site geometry before soil is removed.

  • Mark grids, excavation edges, offsets and safe access routes.
  • Check formation level against benchmark and drainage assumptions.
  • Separate reusable soil, unsuitable material and disposal routes.

Punto de control: No concrete or blinding should be ordered until excavation depth, bearing condition and level records are confirmed.

Herramientas, equipos y acceso: Laser level, Excavator, Plate compactor, Measuring staff

02

Prepare base, blinding and service penetrations

Create a clean, level and coordinated base before reinforcement starts.

  • Trim soft spots and compact the formation or sub-base.
  • Install blinding concrete where specified to protect reinforcement and waterproofing.
  • Fix sleeves and penetrations before reinforcement becomes congested.

Punto de control: Reinforcement should not start until base cleanliness, sleeves and levels are signed off.

Herramientas, equipos y acceso: Compaction tester, Concrete tools, Sleeve templates, String line

03

Place reinforcement, concrete, waterproofing and backfill

Close the foundation only after structural and water-control details are inspectable.

  • Check bar spacing, laps, cover, starter bars and embedded items.
  • Pour concrete with vibration, level control and curing protection.
  • Apply waterproofing, drainage and protection layers before backfill.
  • Backfill in layers with compaction records.

Punto de control: Do not backfill until waterproofing, drainage outlet route and hidden work photos are complete.

Herramientas, equipos y acceso: Rebar bender, Vibrator, Cover blocks, Waterproofing roller, Compactor

Herramientas, equipos y acceso

Earthworks

  • Excavator
  • Plate compactor
  • Shoring tools
  • Dewatering pump

Concrete and reinforcement

  • Rebar cutter and bender
  • Concrete vibrator
  • Screed rail
  • Cover gauge

Waterproofing and drainage

  • Primer roller
  • Torch or membrane tools
  • Drain pipe cutter
  • Protection board knife

Consumos de material para planificaci贸n

Los consumos son referencias de planificaci贸n. Las cantidades finales deben comprobarse con planos, especificaciones, normativa local y fichas de proveedor.

Material o recurso Base Rango de planificaci贸n Unidad Nota
Reinforcement steel Concrete volume 80-140 kg/m3 Concept-stage allowance only.
Blinding concrete Foundation area 0.05-0.08 m3/m2 Matches 50-80 mm layer.
Waterproofing protection board Vertical waterproofed face 1.05-1.15 m2/m2 Allows cuts and laps.
Compacted backfill layers Backfill depth 150-300 mm/layer Layer thickness depends on compaction equipment.

Controles de calidad antes de avanzar

T茅rminos relacionados

Armadura

Elementos de acero que mejoran la tracci贸n del hormig贸n.