Structural frame work sequence

The structure stage must keep load path, geometry, embeds and concrete quality under control. Errors are expensive because they are usually found after walls, services or finishes depend on the frame.

Volver a todas las secuencias

P谩ginas conectadas

Esta secuencia conecta calculadora, checklist y coste de errores para mantener planificaci贸n y riesgo en un sistema.

Secuencia recomendada de trabajo

01

Plan load path, formwork and embeds

Coordinate the frame before concrete hides decisions.

  • Check columns, beams, slabs, openings, construction joints and temporary supports.
  • Confirm embedded plates, sleeves, anchors, balcony edges and stair interfaces.
  • Review pour sequence, access, pump route and curing method.

Punto de control: Do not close formwork until embeds, openings, reinforcement access and pour method are coordinated.

Herramientas, equipos y acceso: Formwork system, Shop drawings, Sleeve templates, Temporary props

02

Fix reinforcement and pour concrete

Deliver structural capacity with inspectable cover, spacing and consolidation.

  • Install rebar with correct laps, chairs, spacers and congestion management.
  • Inspect cover before pour and keep access for vibration.
  • Place concrete in controlled lifts or bays and protect against rapid drying.

Punto de control: Concrete should not be poured until rebar, cover, openings and embeds are signed off.

Herramientas, equipos y acceso: Rebar tools, Cover meter or gauge, Concrete vibrator, Pump line, Curing covers

03

Verify geometry, curing and as-built records

Prevent frame deviations from becoming finish and MEP problems.

  • Check column alignment, slab levels, stair geometry and opening dimensions.
  • Maintain curing period and protect exposed concrete edges.
  • Record as-built deviations before envelope and engineering rough-in.

Punto de control: MEP rough-in and envelope work should not start until critical dimensions and openings are verified.

Herramientas, equipos y acceso: Laser level, Plumb laser, Moisture/curing log, As-built photo set

Herramientas, equipos y acceso

Frame control

  • Laser level
  • Plumb laser
  • Tape
  • Gridline tags

Concrete operations

  • Vibrator
  • Pump hose
  • Concrete bucket
  • Curing sheet

Rebar and embeds

  • Rebar cutter
  • Tie wire tool
  • Cover spacers
  • Embed templates

Consumos de material para planificaci贸n

Los consumos son referencias de planificaci贸n. Las cantidades finales deben comprobarse con planos, especificaciones, normativa local y fichas de proveedor.

Material o recurso Base Rango de planificaci贸n Unidad Nota
Reinforcement steel Structural concrete 90-160 kg/m3 Concept allowance; final design governs.
Formwork contact area Concrete volume 5-10 m2/m3 Depends on wall, column, beam and slab mix.
Curing compound or cover Exposed concrete area 1.00-1.10 m2/m2 Protects early strength and surface quality.
Embed and sleeve allowance MEP crossing or facade support 1 set/item Every embed should have an owner and drawing reference.

Controles de calidad antes de avanzar

T茅rminos relacionados

Ruta de cargas

Ruta continua por la que cargas de cubierta, losas, vigas, muros y columnas llegan a la cimentaci贸n.

Encofrado

Molde y sistema temporal de soporte que mantiene el hormig贸n fresco en la geometr铆a requerida.

Junta de hormigonado

Junta creada donde un vertido se detiene y contin煤a despu茅s, requiriendo continuidad estructural e impermeable.

Curado del hormig贸n

Control de humedad y protecci贸n despu茅s del vertido para que el hormig贸n desarrolle resistencia y durabilidad.