Facade and site works sequence

Facade and site works connect the building to climate, drainage and daily access. The sequence must protect the plinth, direct water away from the building and avoid trapping finished areas behind later earthworks.

Kembali ke semua urutan

Halaman produk terkait

Urutan ini terhubung dengan kalkulator, checklist dan halaman biaya kesalahan agar planning dan kontrol risiko tetap satu sistem.

Urutan pekerjaan yang direkomendasikan

01

Close facade edges, plinth and exposed interfaces

Protect the bottom and outer face of the building before site levels rise.

  • Check plinth height, splash zone, facade base and waterproofing terminations.
  • Install facade finish, cladding or render with movement joints and drips.
  • Coordinate exterior lighting, outlets and penetrations.

Hold point: Site grading should not cover facade or plinth details until they are inspected.

Alat, peralatan dan akses: Scaffold, Render tools, Sealant gun, Drip edge tools

02

Set drainage, grading and hardscape base

Move water away from the structure before final landscaping.

  • Confirm finished floor, external levels and slope away from the building.
  • Install drains, inspection points, channels and stormwater routes.
  • Prepare base layers for paving, paths, ramps and service access.

Hold point: Paving or landscape finishes should not proceed until drainage routes and slopes are checked.

Alat, peralatan dan akses: Laser level, Compactor, Drain laser, Pipe tools, Paver tools

03

Install landscape preparation and final external systems

Finish external areas without damaging facade, waterproofing or access.

  • Install irrigation sleeves, lighting cable routes and planting preparation.
  • Protect completed facade and drains during final soil or paving works.
  • Test exterior lighting, drainage flow and access routes.

Hold point: Final handover of external works should wait until rainwater path, lighting and access are tested.

Alat, peralatan dan akses: Irrigation tools, Cable locator, Lighting tester, Protection boards

Alat, peralatan dan akses

Facade

  • Scaffold
  • Render tools
  • Cladding tools
  • Sealant gun

Drainage and grading

  • Laser level
  • Compactor
  • Pipe tools
  • Drain camera

External systems

  • Irrigation tools
  • Cable locator
  • Lighting tester
  • Protection boards

Norma konsumsi material untuk perencanaan

Rentang konsumsi adalah benchmark perencanaan. Kuantitas final harus dicek terhadap gambar, spesifikasi, kode lokal dan data supplier.

Material atau resource Basis Rentang rencana Unit Catatan
Facade coating Facade surface 0.15-0.30 l/m2/coat Coverage varies by texture and porosity.
Paving base aggregate Paved area 0.10-0.20 m3/m2 Adjust to traffic and soil.
Drain channel allowance Catchment area 0.10-0.30 lm/m2 Planning benchmark before hydraulic design.
Planting soil Planting area 0.15-0.30 m3/m2 Depends on planting depth.

Quality gate sebelum lanjut

Istilah glossary terkait

Plinth

Zona fasad bawah yang bertemu tanah, cipratan air, dan hardscape.