Foundation work sequence

Foundation work should move from verified levels to excavation, base preparation, reinforcement, concrete, waterproofing, drainage and controlled backfill. Skipping checks here makes every later stage more expensive.

Kembali ke semua urutan

Halaman produk terkait

Urutan ini terhubung dengan kalkulator, checklist dan halaman biaya kesalahan agar planning dan kontrol risiko tetap satu sistem.

Urutan pekerjaan yang direkomendasikan

01

Set out excavation and control levels

Translate drawings into real site geometry before soil is removed.

  • Mark grids, excavation edges, offsets and safe access routes.
  • Check formation level against benchmark and drainage assumptions.
  • Separate reusable soil, unsuitable material and disposal routes.

Hold point: No concrete or blinding should be ordered until excavation depth, bearing condition and level records are confirmed.

Alat, peralatan dan akses: Laser level, Excavator, Plate compactor, Measuring staff

02

Prepare base, blinding and service penetrations

Create a clean, level and coordinated base before reinforcement starts.

  • Trim soft spots and compact the formation or sub-base.
  • Install blinding concrete where specified to protect reinforcement and waterproofing.
  • Fix sleeves and penetrations before reinforcement becomes congested.

Hold point: Reinforcement should not start until base cleanliness, sleeves and levels are signed off.

Alat, peralatan dan akses: Compaction tester, Concrete tools, Sleeve templates, String line

03

Place reinforcement, concrete, waterproofing and backfill

Close the foundation only after structural and water-control details are inspectable.

  • Check bar spacing, laps, cover, starter bars and embedded items.
  • Pour concrete with vibration, level control and curing protection.
  • Apply waterproofing, drainage and protection layers before backfill.
  • Backfill in layers with compaction records.

Hold point: Do not backfill until waterproofing, drainage outlet route and hidden work photos are complete.

Alat, peralatan dan akses: Rebar bender, Vibrator, Cover blocks, Waterproofing roller, Compactor

Alat, peralatan dan akses

Earthworks

  • Excavator
  • Plate compactor
  • Shoring tools
  • Dewatering pump

Concrete and reinforcement

  • Rebar cutter and bender
  • Concrete vibrator
  • Screed rail
  • Cover gauge

Waterproofing and drainage

  • Primer roller
  • Torch or membrane tools
  • Drain pipe cutter
  • Protection board knife

Norma konsumsi material untuk perencanaan

Rentang konsumsi adalah benchmark perencanaan. Kuantitas final harus dicek terhadap gambar, spesifikasi, kode lokal dan data supplier.

Material atau resource Basis Rentang rencana Unit Catatan
Reinforcement steel Concrete volume 80-140 kg/m3 Concept-stage allowance only.
Blinding concrete Foundation area 0.05-0.08 m3/m2 Matches 50-80 mm layer.
Waterproofing protection board Vertical waterproofed face 1.05-1.15 m2/m2 Allows cuts and laps.
Compacted backfill layers Backfill depth 150-300 mm/layer Layer thickness depends on compaction equipment.

Quality gate sebelum lanjut

Istilah glossary terkait

Fondasi

Struktur dasar yang menyalurkan beban bangunan ke tanah.

Tulangan

Elemen baja untuk meningkatkan kapasitas tarik beton.

Selimut beton

Jarak antara tulangan dan permukaan beton yang melindungi baja dan menjaga kinerja struktur.